THAT the Delta State Ministry of Works is vital to the success of the state government is evident in its huge, relevant mandate.
Under the watch of the current state governor, Senator(Dr) Ifeanyi Okowa, the ministry has tried to live out the administration’s dream with regard to the accelerated development of roads and related infrastructure. To give fillip to the claim of effective performance by the administration since it was inaugurated into office on May 29, 2015, the Commissioner for Works, Chief James Augoye, at a recent media brief in Asaba, reeled out the sinews of the government’s activities in this regard.
According to Chief Augoye, “road development and construction is a salient factor for the achievement of the SMART Agenda of His Excellency, Senator (Dr) Ifeanyi Okowa’s administration. In line with this realisation, the ministry has embarked on the construction, reconstruction, rehabilitation and maintenance of 193 road projects at a cost of over N122billion between May 2015 and March 2018, covering over 732 kilometres of road and 229 kilometres of concrete –lined drains.
The value of projects currently being handled by the ministry, including those inherited from the previous administration, is put at over N215billion and involves 208 roads with a total length of 866 kilometres. Of this figure, 92 roads, covering over 350 kilometres, have been completed, while 116 roads are at various stages of completion.
Construction of these roads which comprise highways as well as urban roads, is geared towards improved mobility, the stimulation of agricultural and industrial activities, as well as enhancing the quality of life of residents of the state.”
MAJOR HIGHWAY PROJECTS ACROSS THE STATE
In the course of its roughly three years in office, the Okowa administration has undertaken many road projects, ranging from highways to urban and rural riverine ones.
While all of these roads are important and serve virtually the same purposes, the highway segment is considered strategic on account of their ability to simultaneously link many communities. Little wonder, therefore, that the state government, under the watch of Okowa, has accorded it adequate priority attention.
Commissioner Augoye, a the media briefing in Asaba, named the highways projects that had been either constructed, reconstructed and or rehabilitated, by the Okowa government to include the following:
NSUKWA/EJEME-ANIOGOR/AGBOR ALIDINMA/OWA ALIDINMA ROAD
This is a 24-kilometre-long road on which the administration is undertaking rehabilitation and asphalt overlay. It is a major link between Ughelli/Asaba highway and the Uromi/Agbor/Eku/Amukpe road, and spans Aniocha South, Ndokwa West, Ika South and Ika North-East local government areas. Awarded at a cost of N1.6billion, it is almost completed.
OKUREKPO/OKUNOH-OKPARA/OKORUAH/ONUMANE/SAMAGIDI ROAD
Spanning 7.418 kilometres, this road project was awarded to Messrs Setraco Construction Ltd at a cost of N1.1billion, on April 12, 2017, and work on it is already in progress.
MIDDLE SECTION OF ALISIMIE/OZANOGOGO ROAD
Already completed, this road project spans 5.88 kilometres and transverses five agrarian communities in Ika South Local Government Area of the state. Awarded to CCECC Construction, it cost N1.07billion to complete.
UGHELLI/AFIESERE /OFUOMA ROAD
Commissioner Augoye said, in respect of this project, that “the construction of this 8.5kilometre road will ease the difficulties experienced when travelling from the Ughelli Area to Isiokolo, Abraka and other communities in that part of the state. The project was awarded to Messrs CCC Nig. Ltd, at a contract sum of N1, 743, 871, 106.25. The road has been completed and commissioned.”
UMUNEDE/OTOLOKPO/UTE-OKPU/EKUKU-AGBOR/NDEMILI/OBETI/UMUTU ROAD
Spanning across four local government areas at a total of 43.4kilometres, this road project is the single longest ever awarded by the Okowa administration. Commissioner Augoye gave a vivid profile of the project this way, “This 43.4km road is the longest road project awarded by this administration and it cuts across four local government areas of the state providing a link between Umunede and Umutu on the Uromi/Agbor/Eku/Amukpe road. It was awarded on 6th March 2017 to Messrs Mutual Commitment Company Limited (MCC). Work is currently on-going.”
CONSTRUCTIONOF OVIRI-OLOMU/EGODOR ROAD
This road project, awarded to MCC, on the same day as the Umunede/Otolokpo/Ute-Okpu/Ekuku-Agbor/ Ndemili/Obeti/Umutu road, measures 8.56km and cuts across Ughelli South and Burutu local government areas of the state. Work on it is in progress and its completion is expected to open up the impacted communities to new frontiers in socio-economic development.
An attestation to the determination of the government in relation to this project is the severe challenge posed by its difficult terrain.
OTU/JEREMI/OKWAGBE ROAD
This project involves the rehabilitation and re-sealing of the road, which spans 25.60 kilometres with two loops through Owhwha and Oginibo. It was awarded to MCC on March 6, 2017.
UDUOPHORI/TORU-ANGIAMA/TORU-APELEBIRI/PATANI( PHASE 11)
This road spans 4.85 kilometres and contract for its construction was awarded on June 10, 2013, to Messrs Levant Construction Limited. Awarded for N1, 173, 755, 286.11, this impressive road project has since been completed and commissioned. To the relief of the stakeholders, especially residents of the impacted areas, the project has begun to have the desired effect of enhancing the socio-economic fortunes of the communities affected.
URBAN ROADS
The Okowa administration has, since it was inaugurated into office, undertaken many urban road projects. This is with the intention of attaining its goal of enhancing the tempo of the socio-economic development of the state.
Commissioner Augoye, again, at the media briefing, said, “This administration has also embarked on urban renewal by working on several roads in key towns and cities across the state. In this regard, a number of roads have been constructed/reconstructed, rehabilitated and maintained in the three senatorial districts of the state. It is pertinent to mention that this administration has awarded at least one road project in all the local government areas of the state…”
He named the major urban roads undertaken by the administration in urban centres to include:
DUALISATION OF SAPELE ROAD FROM AMUKPE ROUNDABOUT BYSAPELE/WARRI EXPRESSWAY TO A.T. &P, ROUNDABOUT, SAPELE
With the goal of enhancing the pace of the overall development of the state, the Okowa administration has taken action on this road by dualising it. On this specific project, Commissioner Augoye said, “the total length of this project is 7.5kilometres. The entire road has now been dualised by the construction of a concrete median. The Amukpe to Okirighwre segment Junction to A. T & P Roundabout have been expanded from 12.4m and 15m to 18m, respectively.
Walkways are being constructed over the entire length of road, while concrete drains and discharge channels are also being provided as required. The entire road will be strengthened by a layer of asphalt surfacing. The project was awarded to Messrs Levant Construction Limited on 10th December, 2015 at a contract sum of N2, 776, 492, 635.00. The percentage completion is 650% and work is on-going.”
DUALISATION OF OWA-EKEI/OWA-ALERO ROAD
This project is in Ika North-East Local Government Area. It is 5.721kilometres and is about 85% completed by the construction company, Messrs CCECC, to which it was awarded on February 9, 2016 at a cost of N4, 108, 911, 222.68.
JOSEPH EBOLO AND MADONNA SCHOOL ROAD, OKPANAM
This project involves construction work. Commissioner Augoye profiled it this way, “This project was awarded on February 14, 2016 to Messrs Lebtech Construction Company Ltd, at a contract sum of N624, 579, 358.05 and later reviewed on 13th July, 2017 to N1,099, 82, 940.95, with a total length of 4.844km. The project is completed and commissioned.”
KWALE TOWNSHIP ROADS
These are the roads that come under the package handled by the Okowa administration in Kwale, administrative seat of Ndokwa West Local Government Area of the state. “The roads include Ist Iyiatu, Nzebo, Onyeloni, Atokku/Odagwe, Ossai and Isumpe streets, with a total length of 3.233 kilometres. The works were executed at a contract sum of N468.6m and were awarded to Messrs Omelfex Melenco Ltd on the Ist of June, 2016. The project is 100% completed, “ according to Commissioner Augoye.
ABRAKA TOWNSHIP ROADS Road projects handled in Abraka, seat of the Delta State University (DELSU), the state –owned university, are Winners Road and Jehova/Umomnu Crescent.
According to Commissioner Augoye, “the construction of this 1.51km length of road is part of this government’s inter-city road development programme aimed at giving our towns and cities a facelift as well as improving traffic flow. This project was awarded to Messrs Levant Construction Ltd on 9th of December, 2016m at the contract sum of N386.7million. This project has been completed and commissioned.”
UGBOMRO ROAD
This 2.6 kilometre length road is a vital link between the Federal University of Petroleum Resources, (FUPPRE), Effurun/Ughelli dual carriageway, the East/West road and Delta Steel Complex (DSC) Expressway. The contract was awarded on May 26, 2016 to Setraco Nigeria Ltd, at the sum of N994.4m, and has since been completed.
MAXIAL ROAD, OKERENKOKO
Commissioner Augoye explained, at the media briefing, that “this 1.5km length of rigid concrete pavement road with a 20m long single span bridge, was awarded at the cost of N921m to Messrs Roadwell Contracting Ltd. The road, which has obtained 78.81% of completion, will ease access and also integrate various parts of this riverine community.”
OKPARE/UMOLU/OVWODOKPOKPOR/KIAGBODI ROAD
This road has a span, in terms of length, of 10.8km and it transverses three local government areas of the state. It involved the rehabilitation and resealing of the road and was awarded at a cost of N551m to Setraco Nigeria Ltd on November 29, 2017. It has been completed and commissioned.
OVWIAN ROAD, OFF UDU ROAD
This project involved the reconstruction of the 3.1km of the road in question. It was awarded to Messrs Chioino Global Ventures on February 28, 2017, at a total cost of N371.8million and has since been completed and commissioned. The completion and commissioning for use means that the tempo of socio-economic activities in the area has been significantly boosted on account of the action of the Okowa administration.
ACCESS ROAD TO AWARITSE INDUSTRIAL PARK
Measuring 1.80kilometres in length, this project was awarded to Messrs Knight Brooks Limited on June 16, 2016, for the contract sum of N449million. It is to provide access to the Awaritse Industrial park, which is home to many marine and oil gas companies. It has since been commissioned.
OBITOBON/ELOLO/AJAKOROGBO/ORURU ROAD, OGIDIGBEN
This road measures 2.19km in length and was awarded for N1.1billion to Messrs Metsan Services Ltd; work on it is currently on-going, and its completion is expected to further enhance the pace of the socio and economic development of the impacted areas.
OKOWA’S STORM WATER PROJECTS
A major challenge to wholesome development of the state is the fact of the existence of several severe environmental challenges in different parts of it. This is manifested mainly in the flood and erosion challenges that have not only impaired accelerated development, but also constituted both environmental disaster and even grave security threats to residents of geographically- proximate areas.
Some of these challenges are being tackled by the state government via the NEWMAP (Nigeria Erosion and Watershed Project) initiative, in collaboration with the World Bank. In lieu of this NEWMAP project, the Okowa administration has released a total of N530million for the remediation of severe erosion sites in different locations in the state, as part of its counterpart fund and the take-off grant. This development makes Delta State, under the watch of Okowa, to become one of the 22 states of Nigeria to have keyed into the revolutionary initiative.
However, aside of the NEWMAP initiative, the Okowa government is equally tackling other major environmental challenges in different parts of the state. Of note, in this regard, are the various storm water (flood) control projects it is handling in and around Asaba, as part of the overall efforts at responding to the huge flood challenge in the area.
Speaking specifically on these projects, Commissioner Augoye said, inter alia, “Government is currently executing three major storm water routing projects in Asaba metropolis. These projects are aimed at mitigating flooding experienced in various parts of the state capital every year. The projects are:
(1)CONTINUATION AND COMPLETION OF THE CONSTRUCTION OF STORM WATER CONTROL MEASURES IN DLA/JESUSU SAVES CORRIDOR IN ASABA
This project comprises surface drains and underground sewers ranging from 1.2 metres to 1.8metres diameter, which are at depths of up to 8 meters in some sections. The project will control the flooding along the DLA (Direct Labour Agency) road and RALPH UWECHUE WAY TO ANWAI RIVER, ASABA
This 3.5 kilometres network of channels will collect all the flow from the Okpanam Road drains as well as other discharges from the uphill areas of Okpanam town that arrive through the adjoining streets, including Chief T. A. Ikukaiwe Avenue, Ifeanyi Uzogo, Dr. Louis Esenwa and Hon. Ken Mozea streets. The scope includes 1050 metres length of 2.4metres x 3.0metres sewer channel, 8.5 metres deep in some sections and 1, 470 metres length of 3.0mx3.0m open channel along the route. The contract was awarded to Messrs CCECC Nig. Ltd on the 25th January, 2018, at the sum of N4.6billion and scheduled for completion in twelve months.”
THE SUCCESSES, THE CHALLENGES
In all, the storm drainage projects are intended to mitigate the flood incidence, enhance accessibility and raise the pace and quality of the socio-economic prospects of the residents of the areas and all others who transverse the vicinity of the projects.
Fortunately, Governor Okowa, at a recent event of a grand reception in his honour at the Cenotaph, hinted that the government would extend its storm water control measures to Warri and other places.
Evidently, from the plethora of projects delivered by it, the Okowa administration has done exceedingly well with regard to the road, drains and bridges sector. This requires no argument, particularly when due account is taken of the sheer number of the projects-208 in all-according to Commissioner Augoye, the quality of the projects, the short interval of time within which they were put into being (three years, roughly), their equitable Jesus Saves basin. The project covers a length of 2.44 kilometres and was awarded to Messrs CCECC Nig. Ltd on 15th of May, 2017, at the sum of N1.7billion. The project has attained about 80% completion.
(2)STORM WATER DISCHARGE CHANNEL ALONG DBS/CABINET/UMEJEI ADUDU WAY TO AMILIMOCHA RIVER
This 4.33kilometres long network of drains and sewers is designed to channel storm water from Mariam Babangida, WAEC and DBS roads to Amilimocha River through the Cabinet Road. It includes 2,500 metres length of 3.0m diameter sewer channel at depths of between 6 and 9 metres in most sections. This project is being executed by Setraco Nigeria Limited at the cost of N5.2billion.
(3)STORM WATER DRAINAGE ALONG distribution and the fact of the prostrate state of the economy which, as the world now knows and appreciates, only recently managed to exit grinding recession.
However, just as in other spheres of human life, there really are no roses without thorns.
Understandably, in spite of its clear success story, the Delta State Ministry of Works, is not without challenges, and the Commissioner, Chief James Augoye, minced no words in admitting to this fact in his brief of the media in Asaba. He said, “The major challenge the ministry is faced with, especially in recent times, is inadequate funding. With the dwindling oil prices and the attendant impact on the revenues of the state, government has to balance the urgent need for roads with other competing demands of governance that require same attention. This is even more imperative because of the capital-intensive nature of road construction, foreign exchange challenges and impact of inflation on the cost of construction inputs, especially equipment and materials. It is pertinent to mention that the terrain of the state also results in additional costs of road construction. This is in respect to poor soil types and swampy nature of some parts of the state which require the replacement of huge quantities of unsuitable materials and provision of several hydraulic structures in erosion-prone areas and the several streams and rivers that abound.
Another major challenge is the unpredictable weather patterns being experienced in this part of the world due to Climate Change. The erratic nature and the resulting short dry periods make the planning of construction works difficult, with attendant delays and impact on costs. “ (The Pointer).